§ 98-45. Permit modifications.  


Latest version.
  • Within six months of the promulgation of a national categorical pretreatment standard, the discharge permit of users subject to these standards shall be revised to require compliance with the standards within the timeframe prescribed by the standards. Where a user, subject to a national categorical pretreatment standard, has not previously submitted an application for a discharge permit, the user shall apply for a discharge permit within 90 days after the promulgation of the applicable national categorical pretreatment standard. In addition, the user with an existing discharge permit shall submit to the director within 30 days after the promulgation of an applicable federal categorical pretreatment standard the information required by section 98-43.

(Ord. No. O-15-11, § I, 4-11-2011)